| Task Id | Task Name | Resource | Task Start | Task End | Percent Complete | Dependencies |
| 1 | Window installation | installation | 2020-01-22 | 2020-01-30 | 100 | NULL |
| 2 | Electrics | NULL | 2020-02-01 | 2020-02-15 | 100 | 1 |
| 3 | Plumbing works | NULL | 2020-02-10 | 2020-03-09 | 100 | 1 |
| 4 | Doorway reconstruction | NULL | 2020-03-10 | 2020-03-26 | 40 | 3 |
| 5 | Leveling the walls | leveling | 2020-03-14 | 2020-04-14 | 10 | 2,3,4 |
| 6 | Leveling the ceilings | leveling | 2020-03-18 | 2020-04-28 | 100 | 2,3,4 |
| 7 | Leveling the floor level | leveling | 2020-03-22 | 2020-04-24 | 35 | 2,3,4 |
| 8 | Painting of ceilings | painting | 2020-04-25 | 2020-05-05 | 0 | 5,6,7 |
| 9 | Painting of walls | painting | 2020-05-06 | 2020-05-21 | 0 | 8 |
| 10 | Installation of flooring | installation | 2020-05-22 | 2020-07-01 | 0 | 9 |